Each 5 years, the roadmap for the way forward for North America’s largest public transit authority is specified by what’s often known as the MTA Capital Program.
Initially a product of the early Nineteen Eighties, and in addition known as the capital plan, it displays the mammoth amount of cash wanted to maintain issues from “falling apart,” as MTA officers themselves have mentioned. It’s the MTA’s long-term upkeep plan, paying for brand new trains, station maintenance, amenities upkeep and much more. (The price range for day-to-day operations is separate.)
“There are elements of this system that are so far gone that you are risking peoples’ ability to get around if you do not fix them,” MTA Chairperson and CEO Janno Lieber mentioned Wednesday in response to a query from THE CITY. “I’m going to be straight up with everybody about that.”
An MTA monitor employee walks between the elevated platforms on the Allerton Avenue station in The Bronx, Jan. 14, 2025. Credit score: Ben Fractenberg/THE CITY
However the work to safe the longer term security and reliability of the area’s transportation community doesn’t come cheaply. And proper now, its future is up on the air with no official approval but.
The proposed 2025-2029 capital program, which MTA officers unveiled in September —and a state assessment board vetoed on Christmas Eve — carries a projected $68.4 billion price ticket, with funding for almost half the plan not but in place.
Greater than $47 billion of the hoped-for work can be allotted to New York Metropolis Transit, the MTA company in control of the subways, buses, Staten Island Railway and paratransit.
It’s a plan that’s nearly totally targeted on holding the sprawling system in good working situation, with little room for what transit sorts generally name “sexy” tasks, similar to subway line extensions or gleaming new practice terminals (assume Second Avenue Subway and Grand Central Madison).
As a substitute, it’s principally about nuts and bolts. Energy techniques, buildings, upkeep retailers and practice yards take precedence. (However there’s additionally the promise of labor on a brand new line between Brooklyn and Queens.)
The proposed plan is 23% bigger than the 2020-2024 plan, which checked in at greater than $55 billion — and is considerably pricier than the primary capital program, for 1982 to 1986, which was authorized at $7.2 billion. After the MTA board signed off on the most recent plan in September, it nonetheless wants the go-ahead from the assessment panel.
Lieber might be in Albany subsequent week in an try to assist make the sale earlier than state lawmakers.
“They have a lot of different balls in the air,” he mentioned Wednesday. “My pitch is always going to be, let’s be straight up with the public, this needs to be funded and I know you can do it.”
So what’s this imply for the tens of millions of New Yorkers who rely each day on the area’s subways, commuter trains and buses? To stand up to hurry, right here’s a information to the place issues stand:
Why was the proposed plan rejected and what occurs subsequent?
Albany legislative leaders — State Senate Majority Chief Andrea Stewart-Cousins (D-Westchester) and Meeting Speaker Carl Heastie (D-The Bronx) — cited a $33 billion deficit as the explanation the assessment board didn’t approve the following five-year capital plan, at the very least not but.
It’s not the primary time a proposed capital plan has been vetoed.
In October 2014, the Capital Program Evaluate Board rejected the $32 billion 2015-2019 proposal and full funding didn’t come by till October 2015.
Lieber mentioned he plans to bluntly make the case for funding the transit system, pointing to the notorious 2017 “Summer of Hell” — which included an A practice derailment in Harlem and several other monitor fires — as fallout from the drawn-out funding combat led the transit system to slip backwards right into a state of emergency.
“If you don’t make the investments, you’re leading them back to the ‘Summer of Hell,’ full stop,” he mentioned.
Whereas the assessment board’s disapproval didn’t take challenge with the main points of the MTA’s proposal, Gov. Kathy Hochul final week mentioned she and the legislature “will determine the best way to fund it” as soon as the transit company resubmits its plan.
Transit advocates described the veto as “alarming.”
Commuters experience a brand new open gangway C practice in Brooklyn, Feb. 10. 2024. Credit score: Ben Fractenberg/THE CITY
“This leaves riders hanging in limbo, while Albany puts its collective head together to come up with a solution for fully funding the plan,” Brian Fritsch, affiliate director of the Everlasting Residents Advisory Committee (PCAC) to the MTA, mentioned Wednesday on the transit company’s month-to-month board assembly.
Fritsch mentioned the advisory committee, which advocates for subway, bus and commuter rail riders, will quickly publish a report detailing “nearly two dozen” funding choices for state lawmakers, noting how a funding resolution is a should as a result of, “nothing is cheaper the longer you wait.”
What does this big-ticket price range pay for, actually?
The capital plan covers a dizzying scope of stuff — and powers a small financial system all by itself.
The price range gives a roadmap for sustaining and increasing a regional transit community whose bodily property have an estimated worth of $1.5 trillion. It helps drive New York’s $2 trillion financial system by tasks designed to maintain service in secure, working order and offering entry to every little thing New York has to supply — jobs, faculties, healthcare, leisure, cultural establishments and neighborhoods.
Out of the darkest days: The capital plan backstory
The capital plan for the MTA comes from the transit system’s hardest occasions.
The primary one dates again to 1981, when, below then-Chairperson Richard Ravitch (one of many early boosters of THE CITY), the MTA launched a report outlining the wants of a decrepit system and itemizing beneficial priorities by 1985.
On the time, the system was operating on monetary fumes — and repair was a wreck. For instance, in 1982 trains failed each 7,186 miles on common, in accordance with a 2012 PCAC historical past of the capital plan. These days, it’s extra like 122,000 miles.
Inside months, the state legislature handed a funding measure that gave the MTA the ability to challenge bonds for wanted spending and it created the aforementioned Capital Program Evaluate Board. The subway system was placed on monitor to a long-term journey out of its lowest level.
Every capital program provides a various blueprint for holding the transit system in good working situation.
The plans may also develop the community by tasks such because the Second Avenue Subway, whose growth was mapped out by an allocation of simply over $1 billion all the way in which again within the 2000-2004 capital plan.
The latest capital plan, for 2020-2024, checked in at greater than $55 billion. The proposed 2025-2029 plan, at greater than $68 billion, is 23% bigger.
(Reminder, as talked about above, the five-year capital plan is separate from the MTA’s annual working price range of almost $20 billion.)
Who decides what’s within the capital program?
Within the growing older transit system whose oldest stretches of the subway date again to 1904, fixed funding in maintenance is a should. With out it, service reliability and security are jeopardized.
To construct a capital program, the MTA identifies its priorities and evaluates the form of the almost six million property throughout the system.
Strictly for New York Metropolis Transit — the MTA company that operates the subway, bus, Staten Island Railway and paratransit techniques — these property embrace:
493 stations
6,780 subway automobiles
794 miles of sign tools
250-plus miles of line buildings
326 elevators
231 escalators
5,840 buses
38 bus depots
75 upkeep retailers and practice yards
233 substations
and far more.
These wants are then formed into capital plans, which have historically been funded by a balanced mixture of federal, state, regional, metropolis and MTA cash. These elements are knowledgeable by the 20-Yr Wants Evaluation, mandated by state legislation.
However the proposed capital plan should be signed off on by the MTA board, the assessment board and Albany lawmakers — after which there’s the not-insignificant matter of discovering the cash for all that work.
If it’s authorized, what modifications might riders see?
The largest chunk, near $11 billion, is projected to pay for 1,500 new subway automobiles and 500 new railroad automobiles to interchange ones which have been operating because the Nineteen Eighties.
The plan additionally requires investing $5.4 billion on so-called Communication-Based mostly Practice Management (CBTC) sign upgrades that permit trains to run sooner and nearer collectively — techniques now absolutely in place solely on the L and seven strains and alongside stretches of the E, F, M and R.
The proposed plan would modernize alerts on the 48-mile Broadway line (N, Q, R, W) that spans from Ditmars Boulevard in Queens to Dekalb Avenue in Brooklyn.
It might do the identical for 80-year-old alerts on the Liberty Avenue and Rockaway Traces (A, Rockaway Shuttle) and the stretch of the J and Z strains between Essex and Broad streets in Manhattan.
Different big-ticket tasks embrace upgrading electrical substations and upkeep amenities; making at the very least 60 extra subway stations and 6 commuter rail stops absolutely compliant with the People with Disabilities Act; shopping for 500 new electrical buses; putting in trendy fare gates at greater than 150 stations; strengthening elevated buildings and defending stations from flooding.
An MTA rendering of a proposed Interborough Categorical gentle rail station that might cease close to Flatbush Junction in Brooklyn.
It’s not huge on megaprojects that had been highlights of earlier capital plans, similar to Grand Central Madison, the Lengthy Island Rail Highway terminal that was carved out deep beneath Grand Central Terminal.
The plan does name for $2.75 billion for the beginning of design work and getting shovels within the floor on the Interborough Categorical, the $5.5 billion proposed Brooklyn-Queens hyperlink that might be the MTA’s first light-rail line. However even with these billions, it might be years earlier than that line is operational.
How does congestion pricing match into all of this?
The income from Manhattan automobile tolls that launched Jan. 5 is earmarked just for the present 2020-2024 capital plan, which itself faces a $16.5 billion funding deficit.
Congestion pricing was legislatively created by state lawmakers in 2019 to assist fund the present crop of capital tasks, however is just not but linked to future big-ticket MTA plans.
Future MTA capital applications, beginning with the 2025-2029 plan, would require new and recurring income streams till the state comes up with a devoted solution to fund capital enhancements.
Associated